Indicative delivery times for bushings and tap-changers

This information is available for tap-changers and bushings from our different production sites: Ludvika, Sweden, Zurich, Switzerland, Hefei, China, and Alamo, Tennessee, USA.

Standard delivery times from Ludvika, Sweden.

The delivery times below reflect our general load situation. However, we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. 

Shorter delivery times are also available but are subject to material availability. Please contact our Sales Department if the indicated delivery times do not meet your requirements and material availability. 

Please note that final delivery times are always as per the order acknowledgment.

Present Preliminary Delivery Times (Updated as of April 17, 2024)

TAP CHANGERS
UB.. 14 weeks 
UZ.. 21 weeks     
UCG.. 18 weeks        
UCL.. 18  weeks          
UCC../UCD... 20 weeks    
VUBB.. 14 weeks       
VUCG.. 18 weeks          
VUCL.. 18 weeks
BUSHINGS
GOB 37 weeks
GOB 1050 41 weeks
GOE ≤ 1675 40 weeks
GOE 1800 40 weeks
GOE ≤ 2550 42 weeks
GOE 2600 42 weeks
GOE(2) ≤ 1425 40 weeks
GOE(2) 1675 40 weeks
GOEK On request
GOM 40 weeks
GOH 22 weeks 
GSA-OA/ARF AF/ED ≤ 170 34 weeks 
GSA-OA/ARF AF/ED 245 34 weeks 
GSA-OO  34 weeks 
GSB 245 30 weeks
GSB 362 30 weeks 
GSB 420 30 weeks 
GSB 550 On request
GSB 800 On request
GSBK 35 weeks
ARF 245 31 weeks
ARF 300          31 weeks
ARF 362          On request
ARF 420          On request
ARF 550         
On request