Delivery times for bushings and tap-changers (Ludvika, Sweden)

Standard delivery times from Ludvika, Sweden. Valid for delivery Ex-works Ludvika after full and firm order.

The delivery times below reflect our general load situation however we reserve ourselves for large orders received during the period in between, which might affect actual delivery time. If the indicated delivery times does not meet your requirements, please contact our sales department. Final delivery times are always as per the order acknowledgement.

Bushing delivery times are applicable for standard oil impregnated bushings with brown insulators and resin impregnated bushings with grey insulators and standard shed profile.

Shorter delivery times available, subject to material availability. Contact our sales department.

PRESENT PRELIMINARY DELIVERY TIMES - updated on November 25, 2020

 TAP-CHANGERS
 UB.. 7 weeks 
 UZ.. 9 weeks     
 UCG.. 8 weeks        
 UCL.. 8 weeks          
 UCC../UCD... 15 weeks    
 VUBB.. 7 weeks       
 VUCG.. 8 weeks          
 VUCL.. 8 weeks
 BUSHINGS
 GOB 9 weeks
 GOB 1050 10 weeks 
 GOE ≤ 1425 10 weeks  
 GOE 1675 11 weeks 
 GOE 1800 15 weeks 
 GOE ≤ 2550 19 weeks
 GOE 2600 19 weeks
 GOE(2) ≤ 1425 10 weeks 
 GOE(2) 1675 11 weeks 
 GOEK 26 weeks 
 GOM 10 weeks
 GOH 7 weeks 
 GSA-OA ≤ 170 9 weeks 
 GSA-OA 245 11 weeks
 GSA-OO  9 weeks 
 GSB 245 13 weeks
 GSB 362 13 weeks 
 GSB 420 17 weeks
 GSB 550 15 weeks
 GSB 800 15 weeks
 GSBK 17 weeks